# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 114


No crossing is to take place until a monitoring regime and the Geotechnical Design Report (GDR as defined by the DMRB CD622 Managing Geotechnical Risk) is agreed and certified by the WM.

---
Source: https://www.legislation.gov.uk/uksi/2023/1033/schedule/9/paragraph/114 (the official version)
Page: https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-9/paragraph-114
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.