  "legislation": "uksi/2023/1033",
  "legislation_title": "The Awel y Môr Offshore Wind Farm Order 2023",
  "legislation_url": "https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023",
  "path": "schedule/9/paragraph/120",
  "kind": "paragraph",
  "number": "120",
  "heading": null,
  "text": "The undertaker (or any person carrying out works on its behalf) must have and maintain in force for the duration of any works to or within the strategic highway network, public liability/third party insurance to the sum of £10 million covering its liability under paragraph 119. The undertaker must provide evidence of such insurance to the WM if requested.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 9 para. 120 in force at 11.10.2023, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2023/1033/schedule/9/paragraph/120",
    "retrieved_at": "2026-10-28T21:40:22.905590+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}