  "url": "https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-9/paragraph-128",
  "json_url": "https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-9/paragraph-128.json",
  "legislation": "uksi/2023/1033",
  "legislation_title": "The Awel y Môr Offshore Wind Farm Order 2023",
  "legislation_url": "https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023",
  "path": "schedule/9/paragraph/128",
  "kind": "paragraph",
  "number": "128",
  "heading": null,
  "text": "(1) Where, in the reasonable opinion of the WM, any reinstatement carried out by the undertaker is defective, three defect inspections will be carried out comprising:\n(a) A joint inspection by the WM and the undertaker to determine the nature of the failure and what remedial works need to be carried out;\n(b) Inspection by or on behalf of the WM of remedial works in progress; and\n(c) Inspection by or on behalf of the WM when remedial works have been completed.\n(2) The undertaker must pay an inspection fee of £47.50 for each inspection carried out under this paragraph.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 9 para. 128 in force at 11.10.2023, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2023/1033/schedule/9/paragraph/128",
    "retrieved_at": "2026-10-28T21:40:22.905590+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}