# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 146


The undertaker must use all reasonable endeavours to ensure the route of the undertaker cables is designed to cross the Company cables at a horizontal angle which is as close as possible to a right angle as is practicable having due regard to other route requirements.

---
Source: https://www.legislation.gov.uk/uksi/2023/1033/schedule/9/paragraph/146 (the official version)
Page: https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-9/paragraph-146
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.