# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 147: Requirement for notification of start of works

Extent: E+W

(1) The undertaker must give the Company no less than 15 working days’ written notice of its intention to carry out any specified work providing—
(a) the nature of the specified work; and
(b) the anticipated dates of commencement and completion of the specified work.
(2) In the event of the specified work not being commenced within 15 working days of the anticipated date of commencement as notified by the undertaker pursuant to sub-paragraph (1) the undertaker must re-notify the information referred to in sub-paragraph (1).

---