# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 158: Restrictions on anchors and moorings

Extent: E+W

The undertaker must not deploy anchors or other ground mooring equipment within 250 metres of the Company cables unless in accordance with DNV Standards or otherwise except on obtaining, for those anchors or ground mooring equipment, written agreement of the Company (or the written agreement of representative of the Company supervising the work in terms of paragraph 164).

---