  "url": "https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-9/paragraph-78",
  "json_url": "https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-9/paragraph-78.json",
  "legislation": "uksi/2023/1033",
  "legislation_title": "The Awel y Môr Offshore Wind Farm Order 2023",
  "legislation_url": "https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023",
  "path": "schedule/9/paragraph/78",
  "kind": "paragraph",
  "number": "78",
  "heading": null,
  "text": "The undertaker must, no later than 28 days from the date that the documents referred to in article 40 (certification of plans etc.) are certified by the Secretary of State, provide a set of those documents to Network Rail in an electronic format.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 9 para. 78 in force at 11.10.2023, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2023/1033/schedule/9/paragraph/78",
    "retrieved_at": "2026-10-28T21:40:22.905590+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}