# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 85


To ensure its compliance with this Part, the undertaker must before carrying out any specified works and at the undertaker’s own cost, carry out all surveys reasonably necessary to confirm the actual position of apparatus unless otherwise agreed with the Company in writing, such agreement not to be unreasonably withheld or delayed. The Company shall provide on request any reasonable assistance required from the Company of the location of any apparatus.

---
Source: https://www.legislation.gov.uk/uksi/2023/1033/schedule/9/paragraph/85 (the official version)
Page: https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-9/paragraph-85
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.