# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 87: Expenses

Extent: E+W

(1) Subject to the following provisions of this paragraph, the undertaker must pay to the Company on demand all reasonable charges, costs and expenses reasonably incurred by the Company direct consequence of the execution of any specified works including without limitation in respect of—
(a) the approval of plans and method statements;
(b) the carrying out of protective works (including any temporary protective works and their removal);
(c) the survey of any land, apparatus or works, the inspection and monitoring of any specified works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such specified works referred to in this Part of this Schedule; and
(d) any additional costs incurred in the decommissioning of Rhyl Flats Offshore Wind Farm as a result of the specified works.

---
Source: https://www.legislation.gov.uk/uksi/2023/1033/schedule/9/paragraph/87 (the official version)