# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 92

Extent: E+W

(1) Prior to the commencement of any offshore piling as part of the authorised development the undertaker must submit to, and have approved in writing by Conwy County Borough Council, an OPNMP.
(2) The OPNMP submitted and approved under sub-paragraph (1) must be in accordance with the outline OPNMP.

---
Source: https://www.legislation.gov.uk/uksi/2023/1033/schedule/9/paragraph/92 (the official version)
Page: https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-9/paragraph-92
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.