OpenLegislation

Article 5 Power to make subsidiary works

Original text. Later amendments are not shown.

(1)

Subject to the provisions of this Order the Borough may from time to time within the limits of deviation or on any land vested in the Borough at the date of this Order or to be acquired or used by the Borough for the purposes of this Order, erect, construct and maintain, whether temporarily or permanently, all such works and conveniences as may be requisite or expedient for the purposes of, or in connection with, the construction, maintenance and use of the works authorised by article 3.

(2)

On the completion of any part of the works authorised by article 3 the Borough shall remove all temporary works placed by it under the powers of this article.

(3)

The Borough may, on any lands abutting on lands within the limits of deviation, execute or do by agreement with the owners and occupiers of the first mentioned lands any of the works or things referred to in paragraph (1) and any works necessary or convenient for the purpose of providing or facilitating access to or from all the said lands or for preserving the amenities thereof.

(4)

In the exercise of the powers contained in this Order, the Borough shall cause as little detriment and inconvenience to any person as circumstances admit and shall pay compensation to all persons for any loss or damage sustained by them by reason of the exercise by the Borough of such powers and any question as to the amount of the compensation to be so paid shall be determined by the tribunal.