# The Beacon Fen Energy Park Order 2026, Paragraph 154: Retained apparatus: protection


The undertaker must give to VDEC not less than 28 days’ written notice of its intention to commence the construction of any specified works and, not more than 14 days after completion of their construction, must give VDEC written notice of the completion.

---
Source: https://www.legislation.gov.uk/uksi/2026/1025/schedule/11/paragraph/154 (the official version)
Page: https://openlegislation.uk/beacon-fen-energy-park-order-2026/schedule-11/paragraph-154
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.