# The Beacon Fen Energy Park Order 2026, Paragraph 188: Liability


(1) Subject to sub-paragraph (2), if by reason or in consequence of the construction of any specified work or any subsidence resulting from any such work any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised works) or property of NGED the undertaker is to—
(a) bear and pay the cost reasonably incurred by NGED in making good such damage or restoring the supply; and
(b) reimburse NGED for any other expenses, loss, damages, penalty or costs reasonably and properly incurred by NGED, by reason or in consequence of any such damage or interruption.
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of NGED, its officers, servants, contractors or agents.
(3) NGED must give the undertaker reasonable notice of any such claim, including third-party claims, or demand and no settlement, admission of liability, compromise, or demand is to be made without the consent of the undertaker, unless payment is required in connection with a compensation scheme. If the undertaker withholds such consent, NGED is to have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
(4) NGED must act reasonably in relation to any claim or demand served under sub-paragraph (1) and use its reasonable endeavours to mitigate and minimise any costs, expenses, loss, demands, proceedings and penalties to which a claim or demand under sub-paragraph (1) applies and at all times act reasonably and in the same manner as it would as if settling third party claims on its own behalf from its own funds.
(5) NGED’s liability to the undertaker for negligence or breach of contract, in respect of each diversion, shall be limited to the value of that diversion and NGED shall not otherwise be liable to the undertaker for any losses or costs incurred by the undertaker resulting from delays to the authorised development as a result of its failure to undertake works to deliver any alternative apparatus.

---
Source: https://www.legislation.gov.uk/uksi/2026/1025/schedule/11/paragraph/188 (the official version)
Page: https://openlegislation.uk/beacon-fen-energy-park-order-2026/schedule-11/paragraph-188
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.