# The Beacon Fen Energy Park Order 2026, Paragraph 197: Retained apparatus within the Bicker Drove interface area: protection


The undertaker must consult with Bicker Drove on the plans and formulation of the proposed method of working and timing of execution of any specified works within the Bicker Drove interface area, not less than 56 days prior to such works commencing and have regard to reasonable representations received from Bicker Drove made at least 28 days prior to such works commencing.

---