OpenLegislation

Paragraph 38 Interface with the Lincolnshire Reservoir Project

Original text. Later amendments are not shown.

The undertaker will not unreasonably withhold consent for Anglian Water to enter onto land within the undertaker’s control to undertake pre-consent surveys and site investigations as reasonably necessary for the preparation of the Lincolnshire Reservoir Project development consent order application, subject to the undertaker being given—

(a)

at least 14 days written notice of any non-intrusive surveys;

(b)

at least 28 days written notice of any intrusive surveys,

and Anglian Water will comply with any conditions reasonably imposed by the undertaker in granting such consent and will reimburse the undertaker any costs reasonably incurred by it in facilitating the undertaking of the surveys.