# The Beacon Fen Energy Park Order 2026, Paragraph 54: Arbitration


Save for differences or disputes arising under paragraph 134(2), 134(4), 47(1) and 136(11) any difference or dispute arising between the undertaker and National Gas under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Gas, be determined by arbitration in accordance with article 43 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2026/1025/schedule/11/paragraph/54 (the official version)
Page: https://openlegislation.uk/beacon-fen-energy-park-order-2026/schedule-11/paragraph-54
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.