Paragraph 82
The undertaker must consult with Heckington Fen in the formulation of the proposed method of working and timing of execution of the undertaker’s works within the Interface Area, not less than 60 days prior to such works commencing, and have regard to reasonable representations received from Heckington Fen made at least 30 days prior to such works commencing.