  "url": "https://openlegislation.uk/beacon-fen-energy-park-order-2026/schedule-11/paragraph-85",
  "json_url": "https://openlegislation.uk/beacon-fen-energy-park-order-2026/schedule-11/paragraph-85.json",
  "legislation": "uksi/2026/1025",
  "legislation_title": "The Beacon Fen Energy Park Order 2026",
  "legislation_url": "https://openlegislation.uk/beacon-fen-energy-park-order-2026",
  "path": "schedule/11/paragraph/85",
  "kind": "paragraph",
  "number": "85",
  "heading": null,
  "text": "The undertaker must at all reasonable times during construction of the undertaker’s works in the Interface Area allow Heckington Fen and its servants and agents reasonable access to the Interface Area and all reasonable facilities for inspection of the works within the Interface Area.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/1025/schedule/11/paragraph/85",
    "retrieved_at": "2026-10-28T20:54:55.261956+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}