# The Beacon Fen Energy Park Order 2026, Paragraph 12: Construction environmental management plan


(1) No part of the authorised development may commence until a construction environmental management plan (which must be in accordance with the outline construction environmental management plan) for that part has been submitted to and approved by the relevant planning authority, or, where the part falls within the administrative areas of more than one of the relevant planning authorities, each of the relevant planning authorities, in consultation with Lincolnshire County Council and the Environment Agency.
(2) All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan.
(3) Any construction environmental management plan submitted must include a commitment to regularly share all relevant pre-construction, construction, post-construction and operational survey and monitoring data in the appropriate formats with the relevant local environmental records centre(s) and relevant national/regional environmental recording schemes.

---
Source: https://www.legislation.gov.uk/uksi/2026/1025/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/beacon-fen-energy-park-order-2026/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.