Paragraph 6 Battery safety management
Work No. 2 must not commence until a battery safety management plan has been submitted to and approved by the relevant planning authority.
The battery safety management plan must prescribe measures to facilitate safety during the construction, operation and decommissioning of Work No. 2.
The battery safety management plan must be in accordance with the outline battery safety management plan.
The relevant planning authority must consult with the Environment Agency, North Kesteven District Council and Lincolnshire Fire and Rescue before determining an application for approval of the battery safety management plan.
The battery safety management plan must be implemented as approved and maintained throughout the construction, operation and decommissioning of the authorised development.