# The Beacon Fen Energy Park Order 2026, Schedule 7: TRAFFIC REGULATION MEASURES


(1) Area
(2) Extent of temporary traffic signal and banksman control area
Halfpenny Toll Lane
Extents of banksman control and temporary traffic signal control to enable street works for the improvement of access 2/01 in the area shaded green shown on sheet 2 of the streets, rights of way and access plans.
Halfpenny Toll Lane
Extents of banksman control and temporary traffic signal control to enable street works for the improvement of access 2/03 in the area shaded green shown on sheet 2 of the streets, rights of way and access plans.
Heckington Road
Extents of banksman control and temporary traffic signal control to enable street works for the creation of access 4/01 and improvement of access 4/02 in the area shaded green shown on sheet 4 of the streets, rights of way and access plans.
Howell Fen Drove
Extents of banksman control and temporary traffic signal control to enable street works for the improvement of access 5/02 in the area shaded green shown on sheet 5 of the streets, rights of way and access plans.
Howell Fen Drove
Extents of banksman control and temporary traffic signal control to enable street works for the creation of accesses 5/05 and 5/06 in the area shaded green shown on sheet 5 of the streets, rights of way and access plans.
A17 Layby
Extents of banksman control and temporary traffic signal control to enable street works for the creation of access 6/01 in the area shaded green shown on sheet 6 of the streets, rights of way and access plans.
A17 Layby
Extents of temporary closure to all non-site traffic, to allow establishment and operation of a construction traffic access to the authorised development between points TTRO-6/01 and TTRO-6/02 as shown on sheet 6 of the streets, rights of way and access plans.
Asgarby Road
Extents of banksman control and temporary traffic signal control to enable street works for the creation of accesses 6/03 and 6/04 in the area shaded green shown on sheet 6 of the streets, rights of way and access plans.
Littleworth Drove
Extents of banksman control and temporary traffic signal control to enable street works for the creation of accesses 7/01 and 7/02 in the area shaded green shown on sheet 7 of the streets, rights of way and access plans.
A17
Extents of banksman control and temporary traffic signal control to enable street works for the improvement of access 8/01 in the area shaded green shown on sheet 8 of the streets, rights of way and access plans.
Carterplot Road
Extents of banksman control and temporary traffic signal control to enable street works for the creation of access 9/02 in the area shaded green shown on sheet 9 of the streets, rights of way and access plans.

---
Source: https://www.legislation.gov.uk/uksi/2026/1025/schedule/7 (the official version)
Page: https://openlegislation.uk/beacon-fen-energy-park-order-2026/schedule-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.