OpenLegislation

Schedule POINTS OF COMMENCEMENT AND TERMINATION

Original text. Later amendments are not shown.

From a point 145 metres southeast of the junction of Wharton Street with Mount Street on the west bank of the Grand Union Canal.

To a point on the east bank of the Grand Union Canal 166 metres southeast of the junction of Wharton Street with Mount Street.

SPAN:

A single span of 23.00 metres (show distance between abutments).

WIDTH:

29.5 metres (total width measured square); consisting of 14.75 metres wide southeasterly bound highway 3 metres wide light well and 11.75 metres wide northwesterly bound highway.

HEADWAY:

2.6 metres minimum (weir to soffit).

CONSTRUCTION:

Pre–stressed concrete beam and composite deck, reinforced concrete abutments to be faced in brick.

WATERWAY:

Grand Union Canal (a minimum clear navigable waterway of 13.5 metres wide).

All of which details are shown on the following plan which is annexed hereto:

Location Plan and General arrangement of bridge and specification plan number CRD/7253/27.