# The Birmingham City Council (Selly Oak New Road Tunnel) Scheme 2007 Confirmation Instrument 2007, Schedule THE FIRST SCHEDULE TO THE SCHEME: PLANS AND SPECIFICATIONS OF THE SELLY OAK BIRMINGHAM CITY COUNCIL NEW ROAD TUNNEL


From point E as marked on the attached plan numbered 2555—379, 464m north of where the A38 Bristol Road crosses the Worcester and Birmingham Canal.
To point F as marked on the attached plan numbered 2555—379, 538.25m north of where the A38 Bristol Road crosses the Worcester and Birmingham Canal.

---
Source: https://www.legislation.gov.uk/uksi/2007/2339/schedule/2 (the official version)
Page: https://openlegislation.uk/birmingham-city-council-selly-oak-new-road-tunnel-scheme-2007-confirmation-instrument-2007/schedule-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.