Part III NOTIFICATION UNDER REGULATION 6(3)
The particulars required for a notification under regulation 6(3) are as follows:—
- 1.
Name and address of the person entitled to drill the borehole.
- 2.
Particulars with scale diagrams, where appropriate, of—
- (a)
the Irish Grid reference of the location of the top of the borehole;
- (b)
its directional path; and
- (c)
its terminal depth and location.
- (a)
- 3.
A description of the operations to be, or being, performed and a programme of work which includes the dates on which operations are expected to start and finish or (if past) the dates they started and finished.