# The Boston Alternative Energy Facility Order 2023, Part 1: DOCUMENTS AND PLANS TO BE CERTIFIED


(1)
Document name
(2)
Document reference
(3)
Revision number
Addendum to the outline ornithological compensation implementation and monitoring plan
9.116
0.0
Access and rights of way plans
4.5
0.0
Book of reference
3.3
2.0
Combined heat and power assessment
5.7
0.0
Compensation addendum
9.112
1.0
Compensation measures document
9.30
4.0
Design and access statement
5.3
0.0
Environmental statement
Volume 1, 6.2
Volume 2, 6.3
Volume 3, 6.4
1.0
Flood risk assessment
6.4.13
0.0
Harbour seal compensation measures document
9.110
0.0
Indicative generating station plans
4.9
2.0
Indicative wharf plans
4.11
0.0
Land plan and Crown land plan
4.2
0.0
Navigation Management Planning Process: Risk to Birds
9.70
0.0
Navigation management plan template
9.80
1.0
Navigation risk assessment
9.27
1.0
Outline air quality and dust management plan
9.39
0.0
Outline air quality deposition monitoring plan
9.51
2.0
Outline code of construction practice
7.1
0.0
Outline construction traffic management plan
7.2
0.0
Outline landscape and ecological mitigation strategy
7.4
4.0
Outline lighting strategy
7.5
0.0
Outline marine mammal mitigation protocol
9.12
3.0
Outline ornithology compensation implementation and monitoring plan
9.81
1.0
Outline surface and foul water drainage strategy
9.4
2.0
Outline written scheme of investigation
7.3
2.0
Register of environmental actions and commitments
7.6
2.0
Roman Bank plan
4.12
0.0
Works plans
4.3
2.0

---
Source: https://www.legislation.gov.uk/uksi/2023/778/schedule/10/part/1 (the official version)
Page: https://openlegislation.uk/boston-alternative-energy-facility-order-2023/schedule-10/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.