The undertaker must implement the measures as set out in the OCIMP approved by the Secretary of State, unless otherwise agreed in writing by the Secretary of State following consultation with all members of the OEG, the relevant statutory nature conservation body and the local planning authority or authorities. In particular—

(a)

for the compensation for disturbance by the increased number of vessels, no hot commissioning of line 2 of Work No. 1A may begin until two full years following the implementation of the relevant measures set out in the OCIMP have elapsed.