# The Boston Alternative Energy Facility Order 2023, Paragraph 11: Code of construction practice


(1) No part of the authorised development may commence until a code of construction practice for that part has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency and the relevant statutory nature conservation body to the extent that it relates to matters relevant to their functions.
(2) The code of construction practice submitted for approval must be substantially in accordance with the outline code of construction practice to the extent that it is applicable to that part and must reflect the mitigation measures set out in the register of environmental actions and commitments.
(3) The code of construction practice submitted under sub-paragraph (1) must include the following—
(a) the construction and phasing programme;
(b) liaison procedures;
(c) complaints procedures;
(d) an air quality and dust management plan detailing air quality and dust monitoring and management measures during construction that must be substantially in accordance with the outline air quality and dust management plan;
(e) construction noise and vibration monitoring and management plan;
(f) a site waste management plan detailing sustainable site waste management measures;
(g) a soil management plan detailing measures to ensure the temporary storage of soils and other material of value will be in accordance with best practice;
(h) details of screening and fencing to be installed during construction;
(i) a materials management plan detailing measures to ensure the safe storage of excavated materials during construction;
(j) a pollution prevention and incident response plan detailing measures to prevent and control the spillage of oil, chemicals and other potentially harmful liquids;
(k) a health and safety plan, including details of how health and safety risks are to be identified and managed during construction;
(l) a surface and foul water drainage plan including measures for the protection of surface and groundwater during construction;
(m) an artificial light emissions management plan;
(n) measures to ensure the restoration of site following completion of construction; and
(o) appropriate procedures to address any unexploded ordnance that may be encountered.
(4) All construction works must be undertaken in accordance with the approved code of construction practice.

---
Source: https://www.legislation.gov.uk/uksi/2023/778/schedule/2/paragraph/11 (the official version)
Page: https://openlegislation.uk/boston-alternative-energy-facility-order-2023/schedule-2/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.