# The Boston Alternative Energy Facility Order 2023, Paragraph 15: Phasing of construction and commissioning of Work Nos. 1 and 2


(1) Subject to sub–paragraph (2), no part of the authorised development may commence until a phasing programme setting out the commencement of construction and the anticipated start of commissioning and the anticipated date of final commissioning for each of Work Nos. 1 and 2 has been submitted to and approved by the relevant planning authority.
(2) The phasing programme must provide for the anticipated date of final commissioning of Work Nos. 1 and 2 as soon as reasonably practicable. The phasing programme must be implemented as approved by the relevant planning authority.

---