# The Boston Alternative Energy Facility Order 2023, Paragraph 28: Fees


(1) Where an application is made to the relevant planning authority for written consent, agreement or approval in respect of a requirement, the fee prescribed under regulation 16(1)(b) of the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012 (as may be amended or replaced from time to time A) is to apply and must be paid to the relevant planning authority for each application.
(2) Any fee paid under this Schedule must be refunded to the undertaker within four weeks of—
(a) the application being rejected as invalidly made; or
(b) the relevant planning authority failing to determine the application within the decision period as determined under paragraph 26(1),
unless within that period the undertaker agrees, in writing, that the fee is to be retained by the relevant planning authority and credited in respect of a future application.

---
Source: https://www.legislation.gov.uk/uksi/2023/778/schedule/2/paragraph/28 (the official version)
Page: https://openlegislation.uk/boston-alternative-energy-facility-order-2023/schedule-2/paragraph-28
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.