Part 3 CONDITIONS
- General conditions
- Vessels
- Agents/contractors/sub-contractors
- Construction environmental management plan
- Piling
- Navigation management plan
- Marine archaeology
- Marine pollution contingency plan
- Marine mammal mitigation protocol
- Landscape and ecological mitigation strategy
- Concrete and cement
- Coatings and treatment
- Spills, etc.
- Removal of temporary structures etc.
- Dropped objects
- Bathymetric surveys
- Sediment sampling
- Reporting of impact sound to the Marine Noise Registry
- Decommissioning
- Notice of completion of licensed activity