# The Boston Barrier Order 2017, Article 9: Power to execute street works

Extent: E+W

The Agency may, for the purposes of and to the extent necessary for the construction of the authorised works, enter upon so much of any existing path or street as is within the Order limits and any street abutting the Order limits or which has a junction with such a street and may break up or open the path or street, or any sewer, drain, or tunnel under it, or tunnel or bore under the path or street.

---
Source: https://www.legislation.gov.uk/uksi/2017/1329/article/9 (the official version)
Page: https://openlegislation.uk/boston-barrier-order-2017/article-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.