# The Boston Barrier Order 2017, Schedule 5: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W

(1)
Area
(2)
Number of land shown on the Order plans
(3)
Purpose for which temporary possession may be taken
Borough of Boston, Lincolnshire
1, 4
Alternative construction access and construction of authorised works
3, 28, 29, 30, 31, 32, 49
Construction access
5
Alternative construction access
6, 7, 47, 48, 50, 50b, 52, 55, 111, 112, 113, 114
Construction of authorised works
8
Construction compound and construction of authorised works
9, 11, 12, 18, 19, 20
Construction of Work Nos. 3A, 3B and 4B
14
Construction of Work No.4B
15
Construction of Work Nos. 3A, 3B and 4B and mitigation works
21
Construction of authorised works and capital dredging works
22, 23, 23a, 24, 25, 26
Accommodation and mitigation works
27
Temporary storage of dredged materials
44
Construction of Work No.4A and Work No.5B and capital dredging works
50c, 51
Construction of Work No.4A
53
Construction of Work Nos. 4A, 8A and 8B
62
Capital dredging works and provision of temporary mooring facilities for fishing vessels
66, 67
Capital dredging works
70
Construction access for Work No.7
71, 107, 108
Construction of Work No.7
72, 73, 74, 75, 76, 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101, 102, 103, 104, 105, 106, 110
Protective works
109
Construction of Work No.5A and Work No.5B

---
Source: https://www.legislation.gov.uk/uksi/2017/1329/schedule/5 (the official version)
Page: https://openlegislation.uk/boston-barrier-order-2017/schedule-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.