Introductory text
Infrastructure Planning
Made 10th March 2016
Coming into force 11th March 2016
The Secretary of State has had regard to the effect of the changes on the Brechfa Forest West Wind Farm Order 2013 as originally made and is satisfied that the changes are not material.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f4 and the further information requested by the Secretary of State from various persons, has decided to make the changes on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order:
Annotations
Footnotes
- f1
-
Company number 2550622. RWE Innogy Limited (formerly RWE Npower Renewables Limited) is the person who applied for the Brechfa Forest West Wind Farm Order 2013.
- f2
-
2008 c.29. Paragraph 2 of Schedule 6 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c.23); by paragraph 72 of Schedule 13 and by Schedule 25 to the Localism Act 2011 (c.20); and by section 28 of the Infrastructure Act 2015 (c.7).
- f3
- f4
-
S.I. 2011/2055. Regulations 6 and 7 were both amended by S.I. 2012/635 and 2015/760.