Explanatory note
(This note is not part of the Order)
This Order amends the Brechfa Forest West Wind Farm Order 2013 (the “principal Order”), which granted development consent under the Planning Act 2008, following an application for a non-material change under paragraph 2 of Schedule 6 to that Act.
This Order authorises changes to the works plans to reflect changes in the limits of deviation; to the felling plans to reflect changes in the amount and location of tree felling required; and to the commencement and termination points of access tracks for Work No. 3.
The revised work plans and felling plans must be submitted to the Secretary of State for certification under new article 18(1A) of the principal Order. Requirement 7 in Part 3 of Schedule 1 to the principal Order requires the authorised development to be carried out in accordance with plans certified under article 18.