# The Brechfa Forest West Wind Farm Order 2013, Article 3: Development consent etc. granted by the Order

Extent: E+W+S

(1) Subject to the other terms of this Order, including the Requirements, the undertaker is granted—
(a) development consent for the authorised development; and
(b) consent for the ancillary works,
to be carried out within the Order limits.
(2) Subject to article 6 (power to deviate), the authorised development shall be constructed in the lines or situations shown on the works plan.

---
Source: https://www.legislation.gov.uk/uksi/2013/586/article/3 (the official version)
Page: https://openlegislation.uk/brechfa-forest-west-wind-farm-order-2013/article-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.