# The Brechfa Forest Wind Farm Connection Order 2016, Article 33: Certification of plans

Extent: E+W+S

(1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of—
(a) the access and rights of way plans;
(b) the archaeological written scheme of investigation;
(c) the book of reference;
(d) the CEMP;
(e) the construction management strategy;
(f) the crown land plans;
(g) the CTMP;
(h) the design drawings;
(i) the dust management plan;
(j) the environmental features plans;
(k) the environmental statement;
(l) the flood consequence assessment;
(m) the frac-out contingency plan;
(n) the habitat management plan;
(o) the heritage designations plans;
(p) the invasive weeds management plan;
(q) the land plans;
(r) the master key plan;
(s) the overall location plan;
(t) the pollution prevention and emergency response plan;
(u) the public rights of way management strategy;
(v) the transport assessment;
(w) the trees and hedges with the potential to be affected plans;
(x) the waste management plan;
(y) the water management plan; and
(z) the works plans,
for certification that they are true copies of the documents referred to in this Order.
(2) A plan or document so certified is to be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

---
Source: https://www.legislation.gov.uk/uksi/2016/987/article/33 (the official version)
Page: https://openlegislation.uk/brechfa-forest-wind-farm-connection-order-2016/article-33
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.