(1) Where an application has been made under paragraph (1) the relevant planning authority shall have the right to request such reasonable further information from the undertaker as is necessary to enable it to consider the application.
(2) If the relevant planning authority considers further information is needed, and the Requirement does not specify that consultation with a Requirement consultee is required, it must, within 14 business days of receipt of the application, notify the undertaker in writing specifying the further information required.
(3) If the Requirement indicates that consultation must take place with a Requirement consultee the relevant planning authority must issue the consultation to the Requirement consultee within 5 business days of receipt of the application and must notify the undertaker in writing specifying any further information requested by the Requirement consultee within 3 business days of receipt of such a request and in any event within 21 business days of receipt of the application.
(4) In the event that the relevant planning authority does not give such notification as specified in sub-paragraph (2) or (3) it is deemed to have sufficient information to consider the application and is not thereafter entitled to request further information without the prior agreement of the undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2016/987/schedule/10/paragraph/2 (the official version)
Page: https://openlegislation.uk/brechfa-forest-wind-farm-connection-order-2016/schedule-10/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.