# The Brechfa Forest Wind Farm Connection Order 2016, Paragraph 25: Decommissioning

Extent: E+W+S

Should the authorised development become redundant (as determined by the undertaker) for operational purposes the undertaker shall submit to the relevant planning authority a decommissioning and restoration plan for its prior written approval. The decommissioning and restoration plan shall be implemented as approved and the decommissioning of the authorised development and the restoration works shall be completed within 24 months following the approval of the decommissioning and restoration plan.

---