No authorised development is to commence within areas identified as being at risk of flooding in the flood consequence assessment until a flood risk management strategy and a flood evacuation plan has been submitted to and approved in writing by the relevant planning authority in consultation with Natural Resources Wales. The works shall be implemented in accordance with the approved strategy and plan.

---