  "url": "https://openlegislation.uk/brechfa-forest-wind-farm-connection-order-2016/schedule-3/paragraph-9",
  "json_url": "https://openlegislation.uk/brechfa-forest-wind-farm-connection-order-2016/schedule-3/paragraph-9.json",
  "legislation": "uksi/2016/987",
  "legislation_title": "The Brechfa Forest Wind Farm Connection Order 2016",
  "legislation_url": "https://openlegislation.uk/brechfa-forest-wind-farm-connection-order-2016",
  "path": "schedule/3/paragraph/9",
  "kind": "paragraph",
  "number": "9",
  "heading": "Highway accesses",
  "text": "(1) No stage of the authorised development is to commence until written details of the design, layout and subsequent removal (to include the restoration of land) of any new temporary means of access or any new permanent means of access to a highway to be used by vehicular traffic, or any alteration to an existing means of access to a highway used by vehicular traffic, has, after consultation with the highway authority, been submitted to and approved by the relevant planning authority in relation to that stage.\n(2) The highway accesses must be constructed in accordance with the approved details under paragraph (1).",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 3 para. 9 in force at 28.10.2016, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2016/987/schedule/3/paragraph/9",
    "retrieved_at": "2026-10-28T23:19:24.119707+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}