# The Brechfa Forest Wind Farm Connection Order 2016, Schedule 7: Streets/rights of way to be temporarily closed

Extent: E+W+S

(1)Span number (excluding UG sections and access routes where no span numbers are defined)
(2)Street or public right of way to be temporarily closed, altered or diverted
(3)Extent of temporary closure, alteration or diversion as shown on the access and rights of way plans
(4)Plan reference
(5)Type of effect
7-8
Street, C2057
50m
A/AR/PS/1
Temporary Closure
10-11
Street, U2218
26m
A/AR/PS/1
Temporary Closure
11-12
PRoW – 29/20/1 Footpath
26m
A/AR/PS/1
Temporary Closure
16-17
Street, A484
44m
A/AR/PS/2
Temporary Closure
17-18
Street,U2220
25m
A/AR/PS/2
Temporary Closure
27-28
Street, C2074
35m
A/AR/PS/3
Temporary Closure
34-35
PRoW -29/10/1
Footpath
26m
A/AR/PS/3
Temporary Closure
37-38
Street, U2207
33m
A/AR/PS/4
Temporary Closure
41-42
Street, B4309
34m
A/AR/PS/4
Temporary Closure
45-46
Street,B4306
34m
A/AR/PS/5
Temporary Closure
52-53
PRoW-28/15/1
BOAT
18m
A/AR/PS/5
Temporary Closure
69-70
Street, U2203
25m
A/AR/PS/6
Temporary Closure
70-71
Street, A48
50m
A/AR/PS/6
Temporary Closure
73-74
Street,C2071
70m
A/AR/PS/7
Temporary Closure
78-79
Street, C2070
40m
A/AR/PS/7
Temporary Closure
83-84
PRoW – 28/20/2
BOAT
55m
A/AR/PS/7
Temporary Closure
86-Underground cable
PRoW – 28/20/1
BOAT
22m
A/AR/PS/7
Temporary Closure
Underground cable
Street, A485
685m
B/AR/PS/2
Temporary Closure
Underground cable
PRoW-2/8/1
Footpath
31m
B/AR/PS/2
Temporary Diversion
Underground cable -87
Street, U2095
44m
B/AR/PS/2
Temporary Closure
94-95
Street, C2048
25m
C/AR/PS/1
Temporary Closure
100-101
Street,U2097
26m
C/AR/PS/1
Temporary Closure
110-111
Street,U2098
26m
C/AR/PS/2
Temporary Closure
115-116
PRoW- 27/32/1
Footpath
29m
C/AR/PS/2
Temporary Closure
117-118
Street,U5550
26m
C/AR/PS/2
Temporary Closure
125-126
Street, U5551
27m
C/AR/PS/3
Temporary Closure
128-129
Street, U5552
25m
C/AR/PS/3
Temporary Closure
130-131
Street, B4301
60m
C/AR/PS/3
Temporary Closure
135-136
PRoW- 27/14/1
Footpath
40m
C/AR/PS/3
Temporary Closure
135-136
PRoW -26/8/1
Footpath
55m
C/AR/PS/3
Temporary Closure
144-145
Street, C1317
27m
C/AR/PS/4
Temporary Closure
152-153
PRoW -26/9/1
Footpath
42m
C/AR/PS/4
Temporary Closure
155-156
PRoW – 26/11/2
Footpath
16m
C/AR/PS/5
Temporary Closure
159-160
Street, A485
50m
C/AR/PS/5
Temporary Closure
166-167
PRoW - 27/5/1
Footpath
25m
C/AR/PS/6
Temporary Closure
171-172
PRoW – 27/10/1
Footpath
58m
C/AR/PS/6
Temporary Closure
171-172
PRoW –27/10/2
Footpath
58m
C/AR/PS/6
Temporary Closure
Access 49
PRoW – 2/1/1A
7.5M
B/AR/PS/1
Temporary Closure
Access 90
PRoW – 27/11/1
150M
C/AR/PS/10
Temporary Closure

---
Source: https://www.legislation.gov.uk/uksi/2016/987/schedule/7 (the official version)