# The Bridgwater Tidal Barrier Order 2022, Paragraph 6


(1) After the purpose of any temporary works has been accomplished the Agency must with all reasonable dispatch, or after a reasonable period of notice in writing from the Harbour Authority requiring the Agency so to do, remove any such temporary works or any related materials which may have been placed below the level of high water by or on behalf of the Agency.
(2) Where the Agency fails to remove such works or materials within a reasonable period after receiving a notice described in sub-paragraph (1), the Harbour Authority may remove the same and may recover the reasonable costs of so doing from the Agency.

---