# British Railways (No. 3) Order Confirmation Act 1994, Works


A reinstatement of part of the former railway between Hamilton and Stonehouse comprising—
Work No. 1 A railway (2,325 metres in length) commencing at Ferniegair by a junction with the Hamilton to Motherwell Railway at a point 160 metres north-east of the bridge carrying Carlisle Road (A74) over that railway and terminating at a point on the said former railway 130 metres west of the bridge carrying Lanark Road (A72) over that former railway; and
Work No. 2 A railway (2,328 metres in length) commencing by a junction with the termination of Work No. 1 and terminating at Larkhall at a point on the said former railway 68 metres north-west of the junction of Caledonian Road with Macneil Street.

---
Source: https://www.legislation.gov.uk/ukla/1994/3/schedule/part/II/crossheading/works (the official version)
Page: https://openlegislation.uk/british-railways-no-3-order-confirmation-act-1994/schedule/part-II/crossheading-works
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.