OpenLegislation

Schedule THE SCHEDULE TO THE SCHEME

Original text. Later amendments are not shown.

The location and specifications of the footbridge are shown on Drawing Numbers MK307/002 and 307/003 attached hereto and the construction of the footbridge shall include:—

  • Points of Commencement and Termination

  • The location of the footbridge shall be immediately west of the existing Marsh Drive road bridge such that the centre line of the new bridge crosses the north bank of the canal 7.64 metres and the south bank 8.26 metres from the centre line of the existing road bridge.

    Clear Square Span15.0 metres
    Maximum Waterway Width5.20 metres
    Minimum Canal Headroom2.77metres