Regulation 2 Amendment of the Building (Fees) (Scotland) Regulations 2004
The Building (Fees) (Scotland) Regulations 2004f1 are amended in accordance with paragraphs (2) to (5).
For the table in Part 1 of the schedule substitute—
“PART 1
Where work has not already started 1. Application for warrant (including issue of warrant) for the construction of a building or the provision of services, fittings or equipment in connection with a building (whether or not combined with an application for conversion or an application for demolition)
- (a)
where the estimated value of the work does not exceed £5,000—
£200
- (b)
where the estimated value of the work exceeds £5,000 but does not exceed £10,000
- (i)
the sum of
£200 plus (ii) for every additional £500 or part thereof exceeding £5,000 £19
- (c)
where the estimated value of the work exceeds £10,000 but does not exceed £20,000—
- (i)
the sum of
£390 plus (ii) for every additional £1,000 or part thereof exceeding £10,000 £22
- (d)
where the estimated value of the work exceeds £20,000 but does not exceed £100,000—
- (i)
the sum of
£610 plus (ii) for every additional £10,000 or part thereof exceeding £20,000 £71
- (e)
where the estimated value of the work exceeds £100,000 but does not exceed £500,000—
- (i)
the sum of
£1,178 plus (ii) for every additional £20,000 or part thereof exceeding £100,000 £117
- (f)
where the estimated value of the work exceeds £500,000 but does not exceed £1,000,000—
- (i)
the sum of
£3,518 plus (ii) for every additional £50,000 or part thereof exceeding £500,000 £202
- (g)
where the estimated value of the work exceeds £1,000,000—
- (i)
the sum of
£5,538 plus (ii) for every additional £100,000 or part thereof exceeding £1,000,000 £287 2. Application for warrant for conversion only £200 3. Application for warrant for demolition only £200 4. Application for amendment of warrant—
- (a)
for additional work whose estimated value exceeds £5,000
The fee calculated in accordance with paragraph 1 but in respect of the additional estimated value of that work only
- (b)
for additional work where no additional estimated value is involved, the estimated value decreases or the increase in the estimated value does not exceed £5,000
£150 5. Application for an amendment to warrant for demolition only or conversion only. £150 6. Application for an extension to warrant. £150 After work has already started 7. Application (after work has already started) for—
- (a)
a warrant (including issue of warrant) for the construction of a building or the provision of services, fittings or equipment in connection with the erection of a building (whether or not combined with an application for demolition)
200% of the fee calculated in accordance with paragraph 1
- (b)
a warrant for demolition only
£250 ”
For the table in Part 2 of the schedule substitute—
“PART 2
Submission of a completion certificate where no warrant granted 8. Submission of a completion certificate where no warrant granted for—
- (a)
the construction of a building or the provision of services, fittings or equipment (whether or not combined with an application for conversion or for demolition )
300% of the fee calculated in accordance with paragraph 1 of Part 1
- (b)
the demolition of a building only
£400
- (c)
the conversion of a building only
£400
- (d)
work carried out by a local authority where it has done so in respect of—
- (i)
a building regulations compliance notice in terms of section 25(8) of the Act;
nil
- (ii)
a continuing requirement enforcement notice in terms of section 26(3) of the Act;
nil
- (iii)
a building warrant enforcement notice in terms of section 27(7) of the Act;
nil
- (iv)
a defective building in terms of section 28(11) of the Act;
nil
- (v)
a dangerous building in terms of section 30(5) of the Act
nil ”
For the table in Part 3 of the schedule substitute—
“PART 3
Discounts under regulation 5(3)(a) and 6(3)(a) 9. Application for warrant, application for amendment of a building warrant and submission of a completion certificate where no building warrant granted—
- (a)
where the estimated value of the work does not exceed £5,000
£40
- (b)
where the estimated value of the work exceeds £5,000 but does not exceed £10,000
£50
- (c)
where the estimated value of the work exceeds £10,000 but does not exceed £15,000
£60
- (d)
where the estimated value of the work exceeds £15,000 but does not exceed £20,000
£70
- (e)
where the estimated value of the work exceeds £20,000 but does not exceed £50,000
£90
- (f)
where the estimated value of the work exceeds £50,000 but does not exceed £100,000
£110
- (g)
where the estimated value of the work exceeds £100,000
10% of the fee calculated in accordance with paragraph 1 of Part 1 10. Application for warrant for conversion only nil 11. Application for warrant for demolition only nil 12. Application for amendment to warrant for demolition only or conversion only nil ”
For the table in Part 4 of the schedule substitute—
“PART 4
Discounts under regulation 5A(3) and 6A(2)(b) 13. Application for warrant, application for amendment of a building warrant and submission of a completion certificate where no building warrant granted—
- (a)
where the estimated value of the work does not exceed £5,000
£20
- (b)
where the estimated value of the work exceeds £5,000 but does not exceed £10,000
£20
- (c)
where the estimated value of the work exceeds £10,000 but does not exceed £15,000
£25
- (d)
where the estimated value of the work exceeds £15,000 but does not exceed £20,000
£30
- (e)
where the estimated value of the work exceeds £20,000 but does not exceed £50,000
£35
- (f)
where the estimated value of the work exceeds £50,000 but does not exceed £100,000
£40
- (g)
where the estimated value of the work exceeds £100,000
3% of the fee calculated in accordance with paragraph 1 of Part 1 14. Application for warrant for conversion only. nil 15. Application for warrant for demolition only. nil 16. Application or amendment to warrant for demolition only or conversion only. nil ”
Annotations
Footnotes
- f1
-
S.S.I. 2004/508 as relevantly amended by S.S.I. 2017/188.