  "url": "https://openlegislation.uk/building-higher-risk-buildings-procedures-england-regulations-2023/regulation-60",
  "json_url": "https://openlegislation.uk/building-higher-risk-buildings-procedures-england-regulations-2023/regulation-60.json",
  "legislation": "uksi/2023/909",
  "legislation_title": "The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023",
  "legislation_url": "https://openlegislation.uk/building-higher-risk-buildings-procedures-england-regulations-2023",
  "path": "regulation/60",
  "kind": "regulation",
  "number": "60",
  "heading": "Contraventions by the regulator not to be subject to enforcement",
  "text": "The following provisions of these Regulations are prescribed for the purposes of sections 35(2) and 35B(7)(a) of the 1984 Act—\n(a) regulation 5 (building control approval applications for HRB work or stage of HRB work: validity and time limit);\n(b) regulation 6(1) and (2) (building control approval applications for HRB work or stage of HRB work: consultation);\n(c) regulation 7(1), (4) to (7), (13) and (14) (building control approval applications for HRB work or stage of HRB work: decisions);\n(d) regulation 9(4) (notice before starting work and further notice when work is “commenced”);\n(e) regulation 13 (building control approval applications for work to existing HRB: validity and time limit);\n(f) regulation 14(1) and (2) (building control approval applications for work to existing HRB: consultation);\n(g) regulation 15(1), (4) to (7), (13) and (14) (building control approval applications for work to existing HRB: decisions);\n(h) regulation 17(4) (notice before starting work and further notice when work is “commenced”);\n(i) regulation 22 (change control applications: validity and time limit);\n(j) regulation 23(1) and (2) (change control applications: consultation);\n(k) regulation 24(1), (4) to (7) and (11)(b) and (d) (change control applications: decisions);\n(l) regulation 30(4) and (6) to (8) (variation of a requirement imposed on a building control approval);\n(m) regulation 41(1) and (2) (completion certificate applications: validity and time limit);\n(n) regulation 42(1) (completion certificate applications: consultation);\n(o) regulation 43 (completion certificate applications: inspection);\n(p) regulation 44(1) to (6) and (8) (completion certificate applications: decisions);\n(q) regulation 45(5), (6), (8), (10) to (15) and (17) (partial completion certificates) except that regulation 45(8) is not prescribed in relation to the regulator consulting a sewerage undertaker;\n(r) regulation 47(6) (regularisation of unauthorised building work);\n(s) regulation 48(5) to (8) (review of regulator’s decisions);\n(t) regulation 53 (section 30A applications: determinations);\n(u) regulation 54 (section 30A applications: appointed persons);\n(v) regulation 59(2) and (4) (electronic submission and directions).",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Reg. 60 in force at 1.10.2023, see reg. 1(1)"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2023/909/regulation/60",
    "retrieved_at": "2026-10-28T21:41:28.011605+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}