# The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, Paragraph 3: October 2023 to April 2024: cases where building control approval lapses before 6th April 2024

Extent: E+W

(1) This paragraph applies where, by virtue of paragraph 1(5)(a) or (b), paragraph 1(1) to (4) ceases to apply in relation to work.
(2) Where this paragraph applies then with effect from the date paragraph 1(1) to (4) ceases to apply in relation to the work (“the cessation date”) the regulator, and not the local authority for the area, is the building control authority in relation to the higher-risk building and accordingly—
(a) the duties and functions of the regulator under section 91 of the 1984 Act apply in relation to the higher-risk building or any proposed higher-risk building;
(b) these Regulations apply to any of the work from the cessation date, and
(c) the 2010 Regulations, to the extent they apply to higher-risk buildings, apply to any of the work from the cessation date.

---
Source: https://www.legislation.gov.uk/uksi/2023/909/schedule/3/paragraph/3 (the official version)
Page: https://openlegislation.uk/building-higher-risk-buildings-procedures-england-regulations-2023/schedule-3/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.