# The Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, Regulation 16: Building control authority’s power to require notifications for work to existing HRB

Extent: E+W

(1) The building control authority may, by notice in writing, require a client—
(a) to notify the building control authority, within a specified period, when a specified point of the work to existing HRB has been reached;
(b) not to cover up specified work for a specified period.
(2) In this regulation, “specified” means specified by the building control authority in the notice referred to in paragraph (1).

---
Source: https://www.legislation.gov.uk/wsi/2025/1321/regulation/16 (the official version)
Page: https://openlegislation.uk/building-higher-risk-buildings-procedures-wales-regulations-2025/regulation-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

