(1) Where the building control authority receives a change control application which is valid, the building control authority must determine it—
(a) within 6 weeks beginning with the date the application is received by the building control authority, or
(b) within such longer period as at any time the building control authority and the applicant agree in writing.
(2) A change control application is valid if it complies with the requirements of regulation 21.

---