(1) The building control authority may, by notice in writing, require a client—
(a) to notify the building control authority, within a specified period, when a specified point of the HRB work or a specified point of the stage of HRB work has been reached;
(b) not to cover up specified work for a specified period.
(2) In this regulation, “specified” means specified by the building control authority in the notice referred to in paragraph (1).

---